Zubair Oil Field Development Project – Degassing Station

Country: Iraq
Client: ENI E&P
Activity: Plant – Oil & Gas

The project consisted of all detailed design for the revamp of the degassing station to increase production to 700 kBOPB.

The project was carried out in three phases:

  1. conversion of existing trains from dry to wet;
  2. renewal of water injection system;
  3. installation of fiscal metering station.

Enereco carried out the review of FEED design and carried out the detailed design as well as activities in support of procurement.